Worldwide Water Engineering and Contracting
News
 
Naston LogoNaston Ltd.
Naston Limited is a leading engineering and contract company in the field of water and wastewater treatment with over 30 year's service to the water industry.

Naston Ltd
The Control Tower
Brooklands
Weybridge
Surrey
England KT13 0YP

Tel: 01932 336611  
Phone calls may be recorded for training and quality purposes.

Fax:+44 (0)1932 336886
Email: enquiries@naston.co.uk


Naston ltd industrial wastewater treatmentCrawley STW Extensions

This contract for the complete mechanical and electrical works associated with the extensions and improvements of Crawley Sewage Treatment Works (adjacent to Gatwick Airport) was awarded by Thames Water utilities Limited in March 1990. The ?2.2 million contract for the mechanical and electrical works was completed on schedule in May 1991.


Crawley STW Extensions

The provision of sophisticated monitoring equipment and networked PLC control throughout the plant together with a full SCADA system was a key feature of the this project.

On completion, a rigorous programme of oxygen transfer testing was conducted in the new Stage 3 aeration tanks to verify the guaranteed performance and to ensure compliance with discharge consent standards.


Naston ltd industrial wastewater treatmentThe mechanical and electrical works at this site feature:

- Fine bubble diffused aeration
- Stormwater pumping
- Return and surplus activated sludge pumping
- Anoxic tank mixing
- Sludge consolidation
- Standby power generation
- Primary tank auto-desludging
- Final Settlement


Naston ltd industrial wastewater treatmentPlant Instrumentaton and Monitoring
Sophisticated equipment installed to monitor existing and Stage 3 flows, levels, pressures, rotation, suspended solids and dissolved oxygen, providing both local control and overall plant monitoring signals.


Crawley STW Extensions

Naston ltd industrial wastewater treatmentElectrical Works
Extensive modifications and additions to existing control panels and installation of new panels together with all necessary cabling were carried out during the course of this contract with minimum disruption to the existing plant operations.

Naston ltd industrial wastewater treatmentFinal Settlement
Half-bridge scraper mechanisms installed in the three new 23 metre diameter final settlement tanks serving the Stage 3 treatment stream. Refurbishment of existing final settlement tanks including the replacement of one half bridge scraper mechanism and installation of scum removal equipment and "V" notch weirplates to the remaining tanks.


Naston ltd industrial wastewater treatmentPlant Control and SCADA
Overall plant control based on five networked PLC's together with a Dexterity SCADA package running on a VAX VMS computer system. Facilities are also provided for separate data interchange between the PLC network and the existing Datacall System to enable designated alarms to be transmitted via the PSTN whilst the works are unmanned.


Naston ltd industrial wastewater treatmentFine Bubble Diffused Aeration
Six variable speed Roots air blowers, each rated 110kW, installed in the existing blower house serving the existing and Stage 3 treatment streams.

Flexible membrane fine bubble diffusers installed in the three new aeration tanks capable of transferring in excess of 500kg of oxygen per hour into the Stage 3 treatment stream. The diffuser installation provides tapered aeration, automatically regulated in response to both primary and secondary dissolved oxygen monitoring.

Extensive refurbishment work was carried out on existing aeration tanks including the installation of new flexible membrane diffusers and replacement of weirstocks and penstocks.


Crawley STW Extensions

Crawley STW Extensions

Naston ltd industrial wastewater treatmentStormwater Pumping
Submersible pump unit rated 132kW installed in the existing main works pumping station forebay, providing additional standby stormwater pumping.

Naston ltd industrial wastewater treatmentReturn and Surplus Activated Sludge Pumping
Three submersible RAS pump units and two submersible SAS pump units installed in the new pumping station, serving the Stage 3 treatment stream.

Naston ltd industrial wastewater treatmentAnoxic Tank Mixing
Two submersible mixer units installed in the new anoxic tank, serving the Stage 3 treatment stream.

Naston ltd industrial wastewater treatmentSludge Consolidation
Automation of the existing sludge consolidation facilities.

Naston ltd industrial wastewater treatmentStandby Power Generation
Diesel driven generating set rated 750 KVA, installed in the main works pumping station and replacing a 375 KVA unit that was prepared, removed and mothballed for long term storage.

Naston ltd industrial wastewater treatmentPrimary Tank Auto-Desludging
Nine rotary lobe pump units installed adjacent to existing primary tanks to provide automatic desludging.

 
Projects Reference
Project Reference List
Powder Process Division
Package Plant Division

Quick Search
 Go